Rediseño e implementación del sistema de control de una planta de separación primaria de hidrocarburos

Show simple item record

dc.contributor.advisor Colon, Daniel es_ES
dc.contributor.other Martínez Coya, Edgardo Max es_ES
dc.coverage.spatial RINCON DE LOS SAUCES ARG 2023-2025 es_ES
dc.creator Gonzalez, Victor Martin
dc.date 2025-05-25
dc.date.accessioned 2025-09-10T16:09:21Z
dc.date.available 2025-09-10T16:09:21Z
dc.identifier.uri https://rdi.uncoma.edu.ar/handle/uncomaid/18990
dc.description.abstract El objetivo del presente proyecto es rediseñar el sistema de control de una planta de separación primaria de hidrocarburos ubicada en la cuenca neuquina. El sistema de control actual, basado en un controlador Fisher ROC 364, está quedando obsoleto, ya que éste y sus periféricos son de fabricación descontinuadas dificultando su mantenimiento. Por otro lado, no permite hacer modificaciones de manera remotas ni parciales en su programación sin afectar el normal funcionamiento del proceso. La actualización de la tecnología, como la implementación de un controlador lógico programable (PLC), permitirá una mayor capacidad de memoria, una programación amigable para futuras modificaciones, mayor velocidad de procesamiento de la CPU, mayor capacidad de manejos de entradas y salidas, mayor velocidad de transmisión de datos al sistema SCADA entre otras. Además, esta tecnología permite instalar un panel HMI (PanelView) en el lugar, lo que facilitará el monitoreo por parte del operador, la elección de operaciones y configuraciones desde el panel sobre el PLC. Para ello se realizará la ingeniería inversa del actual sistema de control y el relevamiento de equipos e instrumentos existentes en la instalación. Se obtendrá el listado de señales y se desarrollará la matriz de causa & efecto que se implementará en el sistema de control. Después se continuará con la selección de un PLC como unidad central del nuevo sistema de control y sus periféricos, luego se definirá la ingeniería del tablero. Posteriormente se realizará el diseño y programación del PLC y Panel HMI. Para finalizar, se hará el precomisionado, comisionado y puesta en marcha del nuevo sistema de control. También se llevará a cabo el análisis de las mejoras debido al cambio de tecnología, en el control del proceso, seguridad de las personas e instalaciones. Además, se realizarán recomendaciones para futuras mejoras. es_ES
dc.description.abstract The objective of this project is to redesign the control system of a primary hydrocarbon separation plant located in the Neuquén basin. The current control system, based on a Fisher ROC 364 controller, is becoming obsolete, since it and its peripherals are discontinued, making maintenance difficult. On the other hand, it does not allow remote or partial modifications to be made to its programming without affecting the normal functioning of the process. The technology update, such as the implementation of a programmable logic controller (PLC), will allow greater memory capacity, friendly programming for future modifications, higher CPU processing speed, greater input and output handling capacity, higher speed of data transmission to the SCADA system among others. In addition, this technology allows an HMI panel (PanelView) to be installed on site, which will facilitate monitoring by the operator, choosing operations and configurations from the panel on the PLC. To do this, reverse engineering of the current control system will be carried out and a survey of existing equipment and instruments in the facility will be carried out. The list of signals will be obtained and the cause & effect matrix will be developed that will be implemented in the control system. Afterwards, the selection of a PLC as the central unit of the new control system and its peripherals will continue, then the engineering of the board will be defined. Subsequently, the design and programming of the PLC and HMI Panel will be carried out. Finally, the pre-commissioning, commissioning and implementation of the new control system will be carried out. The analysis of improvements due to the change in technology will also be carried out, in process control, safety of people and facilities. Additionally, recommendations will be made for future improvements. es_ES
dc.format application/pdf es_ES
dc.language spa es_ES
dc.publisher Universidad Nacional del Comahue. Facultad de Ingeniería es_ES
dc.rights Atribución-NoComercial-CompartirIgual 4.0 es_ES
dc.rights.uri https://creativecommons.org/licenses/by-nc-sa/4.0/ es_ES
dc.subject Batería es_ES
dc.subject PMP es_ES
dc.subject RTU es_ES
dc.subject PLC es_ES
dc.subject HMI es_ES
dc.subject PMG es_ES
dc.subject LIC es_ES
dc.subject SCADA es_ES
dc.subject Migración es_ES
dc.subject.other Ciencias de la Computación e Información es_ES
dc.subject.other Ciencias Puras es_ES
dc.subject.other Ciencias Aplicadas es_ES
dc.title Rediseño e implementación del sistema de control de una planta de separación primaria de hidrocarburos es_ES
dc.type trabajo final de grado es
dc.type bachelorThesis eu
dc.type acceptedVersion eu
unco.tesis.grado Ingeniero Electrónico es_ES
dc.description.fil Fil: Gonzalez, Victor Martin. Universidad Nacional del Comahue. Facultad de Ingeniería. Departamento de Electrotécnia; Argentina. es_ES
dc.cole Trabajos Finales es_ES


Files in this item

This item appears in the following Collection(s)

Show simple item record

Atribución-NoComercial-CompartirIgual 4.0 Except where otherwise noted, this item's license is described as Atribución-NoComercial-CompartirIgual 4.0

Search RDI


Browse

My Account

Statistics